When I planned a move from one AS/400 to another, I had to decide what to move and in what order. The old machine would keep running the business until cutover. Anything copied too early could end up out of date on the new machine if it kept changing on the old one.
I started with an inventory. Programs and files on the AS/400 are grouped into libraries. I used a command called DSPOBJD to collect information about those objects and summarized it in Excel. For each library, I noted what it was used for, how much space it took up, and how often it changed.
If something changed infrequently and we could stop updates on the old machine after moving it, we could move it ahead of time. If the business was still updating it right up to cutover, it went last. It’s like moving house: you can pack up the bookshelf early, but you leave out the tools you’ll still need on moving day.

That gave me a much clearer picture of what had to happen on the day. Finding the biggest library wouldn’t tell me when it could move. The order depended on when we could stop changing it on the old machine.
One note for anyone doing this today: DSPOBJD can give you a list of object names and attributes. That list won’t tell you on its own which things the business will still need to update on cutover day. I’d confirm how often they change, and when those changes can stop, with the people who use them.
The idea was to leave as little as possible for cutover day. That work started with an inventory in Excel.